HydrotechEngineering Trading Enterprise Call +220 337 4143
Temporary works / access

Sintet Access Bridge

Construction of an access bridge crossing to reach the island for the OMVG transmission line.

Sintet Access Bridge, Sintet, delivered by Hydrotech Engineering

An access bridge crossing built at Sintet so the main contractor could physically reach the island and build the OMVG interconnection line.

Enabling works of this kind never appear in the finished photographs, but without them the main contract cannot start. The crossing had to carry plant and material loads across a watercourse and stay serviceable for the duration of the line works.

Have a project to price?

Tell us the scope and the location. You will get a straight answer about whether we are the right contractor for it.